82.Progress made relating to the "University of Jaffna" project. - Roof installation work is going to complete - M/R Roof Slab Shuttering work...!

81.Progress made relating to our project at "No.03, Beach Road Mt.Lavinia" 28 units Apartment project. Transfer floor beam and slab reinforcement work is going on...

80.Progress made relating to the "University of Jaffna" project. - Roof installation work - Gutter slab masonry work - M/R Roof Slab Shuttering work...!

79.News published in Daily Newspaper relating to Mode group of companies No.8, IBC Road, Colombo- 06 stone laying ceremony on 19/02/2021

78.Mode Engineering's one of the Luxury Apartment Project @ No 08, IBC Road, Colombo -06 In terms of the foundation works, Soil testing is in progress.

77.Mode Engineering's one of the Luxury Apartment Project @ No 03, Beach Road, Mount Lavinia In terms of the regular construction progress, we have done the Concrete for the transfer floor columns on 2021.02.16.

76.The Foundation Stone Laying Ceremony of Mode Group’s new luxury condominium project at No. 8A, IBC Road, Wellawatta

.The Foundation Stone Laying Ceremony of Mode Group’s new luxury condominium project at No. 8A, IBC Road, Wellawatta was held on 11th February 2021 at the auspicious time between 9.00 a.m – 10.00 am with the participation of Mode group Chairman - Mr. Anosan, Director – Mrs. Hamsapiriya, General Manager – Major General Bhanawi Soysa, Mode Group’s Employees, Customers, Company Consultants, Investors, Banking partners, Lawyer, professionals & company well-wishers. This Luxury Condominium project is constructed with 08 Residential Floors, comprising 30 units and with 02 levels Car park. This is located in the heart of Wellawatte With Important landmarks such as leading schools, reputed hospitals, supermarkets, banks, public & private institutions is a much-sought advantage. Easy access both from Galle road and the marine drive. This event marked another milestone of Mode Group

75.Ground floor slab concrete has been completed on 2021.02.08 at No.03, Beach Road, Mount Lavinia.

74.Lower ground floor ramp area concrete finished on 2021.01.27 Ground floor slab, beam formworks and reinforcement work on going

73.Happy customers Handing over the keys 28 IBC Road, Wellawatte.

72.Progress made relating to the "University of Jaffna" project. Roof beam shuttering work is going on...!

71.When you step in to our Apartment you have a visually pleasing Modern touch in every Angle.Open and paneled quiet and practicable wide and spacious Balcony with a Beautiful view

70.May this Festival start with streak of luck and Happier days ahead, Happy Pongal 2021.

69.Progress made relating to our project at "No.03, Beach Road Mt.Lavinia" 28 units Apartment project. Lower ground floor to ground floor columns and retaining wall concrete work has been completed successfully.

68.2021 New Year celebration at Head office and site

67.Mode Engineering No.28, IBC Road, Colombo 06 Complete by December 2020 On-time delivery, Quality construction Night view...

66.Progress made relating to our project at "No.03, Beach Road Mt.Lavinia" 28 units Apartment project. Raft foundation concrete has been completed successfully.

65.Progress made relating to our project at "No.03, Beach Road Mt.Lavinia" 28 units Apartment project. 100% of Rafter slab concrete work done

64.Progress made relating to our project at "No.03, Beach Road Mt.Lavinia" 28 units Apartment project. 80% of Rafter slab concrete work done

64.Progress made relating to the "University of Jaffna" project. 1st-floor concrete has been completed.

63.We celebrated Navarathri pooja @ Head office & our construction sites

62.Progress made relating to our project at "No.03, Beach Road Mt.Lavinia" 28 units Apartment project. Raft foundation reinforcement work.

61.Progress made relating to our project at "No.03, Beach Road Mt.Lavinia" 28 units Apartment project. Raft foundation reinforcement work.

61.Another Milestone!! Directors of MODE Group is seen signing the transfer deed of the land situated at, No.8A, IBC Road, Colombo-06. where our 3rd apartment project consisting of 32 units to be constructed before the end of November 2020.

61.Mode Group 3rd Year Celebration.

60." Sri Suboothi National School Battaramulla." project presents site progress.

59.No.28, IBC Road, Wellawatta project enter the finishing level...

58.progress made relating to the "University of Jaffna" project. Shuttering work 1st floor & reinforcement work for staircase

57.No.03, Beach Road, Mt.Lavinia. Current work progress _ Screed concreting at the basement floor

56."Samanakkanda Purana Viharaya, Payagala" the roof work at the stage of finishing.

55.No - 03 Beach Road, Mt Lavinia. luxurious Apartments. Mode Group of company project 02 Current work progress _ Excavation

54.Current View of No.28, IBC Road, Colombo-06

53." Sri Suboothi National School Battaramulla." project present site progress. #Roof_fixing#

52."Samanakkanda Purana Viharaya, Payagala" project present site progress.

51. We are happy to announce our new project in Jaffna, "Conversion of Single Storied Building into three-storied Building and completion of Exam Hall at Centre for Open & Distance Learning, University of Jaffna" and we have initiated the project.

50. Interlock Paving with landscaping pedestrian Facilities along the Canal Reservation at Uttarananda Mawatha Project has been completed on 30 of June 2020.

49. No - 03 Beach Road, Mt Lavinia. Luxurious Apartment. Mode project 02 Current work progress _ Shoring work

48. Current progress at 28 , IBC RD , CL06
-All structural work completed
-100% masonary work completed
-80% Electrical work completed
-70% plumping work completed
-40% painting work completed
-10% waterproofing works progressing
-Tile , Aluminium, lift. Wooden doors and pantry works are in preparation level

47. Painting work started

46. How to invest in Real Estate??? make sure your hard earn money investment in right place!!!

45. Mode Group of Companies proudly Launched Affordable Luxury Apartments at No.03, Beach Road, Mount Lavinia. on 09th March 2020. ( A Truly Designed 6 levels residential floor and 2 levels car park Luxurious Condos )

44. Our project progress of interlock Paving with landscaping pedestrian Facilities along the Canal Reservation at Uttarananda Mawatha Project...

43. Rooftop concrete work successfully completed on 23/02/2020.

42. No.28, IBC Road, Wellawatte final rooftop work is progressing .

41. No.28, IBC Road Wellawatta Luxury Apartment 8th-floor concrete work successfully completed on 02/02/2020.

40. No.28, IBC Road Wellawatta Luxury Apartment 7th-floor concrete work successfully completed on 14/01/2020.

39. Progress at Sri Suboothi National School Battaramulla.

38. As one year ends(2019) and a new one starts(2020). Let me wish for you joy and lightness of heart. May you, my employees have a beautiful New Year. And make this one special for all you hold dear.

37. No.28, IBC Road Wellawatta Luxury Apartment 6th-floor concrete work successfully completed on 22/12/2019.

36. Our project progress of interlock Paving with landscaping pedestrian Facilities along the Canal Reservation at Uttarananda Mawatha Project...

35. No.28, IBC Road Wellawatta Luxury Apartment 5th-floor concrete work successfully completed on 01/12/2019.

34. Repair Works At Sri Suboothi National School Battaramulla. parapet wall construction in progress ...

33. We have obtained ISO Certification award for all construction projects. Mode Engineering maintain their quality constructions

32. Pedestrian Facilities Along the Canal Reservation at Uttarananda Mawatha Project. Paving interlock is going on...

31. No.28, IBC Road Wellawatta Luxury Apartment 4th-floor concrete work successfully completed on 08/11/2019.

30. "Samanakkanda Purana Viharaya, Payagala" project present site progress(22/10/2019).

29. No.28, IBC Road Wellawatta Luxury Apartment 3rd-floor concrete work successfully completed on 20/10/2019.

28. No.28, IBC Road apartment 3rd-floor reinforcement and formwork in progress(14/10/2019)

27. IBC LUXURY APARTMENT 2nd-FLOOR CONCRETING - 27/09/2019

26.Pedestrian Facilities Along the Canal Reservation at Uttarananda Mawatha Project.

Stage 01 completed successfully and stage 02 site area was cleaned and up to 22m concrete curb leveled for laying interlock(26/9/2019)

25. Repair Works At Sri Suboothi National School Battaramulla. - Current progress update (30/09/2019)

24. We successfully transferred the deed No.03 Beach Road, Mount Lavinia, under Mode Engineering (Pvt) Ltd on - 10/09/2019

An opportunity to purchase Mount Lavinia markable place. Our another dream project coming in No,03, Beach Road, Mount Lavinia, Mode Engineering (Pvt) Ltd successfully transfer the deed of Beach Road, Mount Lavinia for the new project.

23. 1st-floor column work completed on- 14/09/2019

22. IBC Luxury apartment 1st-floor concreting - 03/09/2019

21. Progress of 1st-floor formwork - 30/07/019

The Excitement is now building up as we get closer to 1st-floor work at 28 ,IBC RD ,CL06 The Ground floor & Basement parking levels almost completed.
(planning to lay massive concrete for transfer floor concrete on 20th August 2019)

20. Ground floor column work - 14/06/2019

Ahead of the Scheduled Program at Mode Residencies,28, IBC Road , wellawatte – We have completed Piling, Basement, Car Park and ready with First Floor slab work now.

19. Modernization of Schools under the Nearest School-10/09/2019

Modernization of Schools under the Nearest School, Best School program initiated by Ministry of Education Repair Works at Sri Suboothi National School Battaramulla awarded by the Ministry of Education under Nearest School Best School Program.
Project Value Rs. – Rs 16.3 million

18. Modern Urban Development in Sri Lanka- 09/07/2019

Pedestrian Facilities Along the Canal Reservation at Uttarananda Mawatha – Under the Fort Development Project -Pedestrian Web Stage IV- awarded by the Urban Development Authority.
Project Value Rs. – Rs 11.9 million

17. Restoration of Cultural Heritage Conservation of Image House- 25/05/2019

Professional Partnership in Conservation and Restoration of Cultural Heritage Conservation of Image House at Samanakkanda Purana Viharaya, Payagala. awarded by the Central Cultural Fund- Ministry of Housing Construction & Cultural Affairs.

Project Value Rs. – Rs 25.5 million

16. Progress Update –IBC Road, Mode Residencies- 10/06/2019

Progress update – MODE ENGINEERING, 28 IBC Road, Colombo-06.

Ongoing Excavation& Pile Cap work Phase 02 (Excavation, Pile Hacking, Dewatering & Pile Cap concreting)

15. Progress Update –IBC Road, Mode Residencies- 18/05/2019

Ongoing concrete work Phase 01 (Basement Column & Retaining wall )

14. Renovation of Principal’s Office at Kalutara Vidyalaya

Mode Engineering ( Private ) Limited has been awarded the Contract for “ Renovation of Principal’s Office at Kalutara Vidyalaya “ initiated by the Ministry of Education under the “ Nearest School Best School “ Program in April 2019.

13. London Tamil Market in London

MODE Engineering ( Private ) Limited is pleased to announce that we have successfully concluded the Business Program conducted by the British Chamber of Commerce for London Tamil Market – 2019 in Leisure Centre, Harrow on 6th & 7th April 2019 attended more than 10000 participants seeking investments & business opportunities.

12. 28, IBC RD, COLOMBO 06 Project - 15/02/2019

Progress update shoring work 75% completed

11. Smart Classroom Project Handed Over

The Ministry of Education has awarded Converting Existing Two Numbers Classroom into smart Classroom and Construction of New Two Classroom Building at Vivekananda Maha Vidyalaya, Colombo to Mode Engineering (Pvt) Ltd.

Converting in to Smart Classroom and Construction of Classroom Building, Vivekananda College, Colombo project was completed and handed over  Converting & Construction of Smart Classrooms at Vivekananda Maha Vidyalaya  , Colombo 13.

  • Project Value Rs. – Rs 6.2 million
  • Date of Completion – 31.05.2019

10. LANKA PROPERTY WEB SHOW 2019

Mode Engineering (Private) Limited participated at the Grand Show held on February 8 th & 9 th 2019 in Kingsbury Colombo and provided CONSTRUCTION NEWS on Mode Residencies to all participants & investors.

9. The University of Jayawardenapura Project - 01/04/2019

The University of Jayawardenapura new vehicle park facility the project was completed and handed over on 01/04/2019.

Project Value Rs. – Rs 3.77 million

Date of Completion – 1/04/.2019

8. Pile mobilization completed. - 26/01/2019

7. Block Work & Wall Finish With Bar Counters at Proposed Sports Bar & Restaurant Water’s Edge project was completed and handed over on 16/03/2019.

The Water’s Edge Limited Has Awarded Block Work & Wall Finish with Bar Counters at Proposed Sports Bar & Restaurant Project at the Water’s Edge Premise to Mode Engineering (Pvt) Ltd. This Project Was Completed Within A Period Of 01 Month At A Total Cost Of LKR 3.6 Million.

6. No.28, IBC Road, Wellawatta Foundation Ceremony- 22/10/2018

One of our big dream project No.28, IBC Road, Wellawatta foundation ceremony held on 22/10/2018, Participated Bank managers, Staff, Sub Contractors Chairmen’s.

5. Demolishion work completed - 01/10/2018

4. transferred the deed No.28, IBC Road

We successfully transferred the deed No.28, IBC Road, Colombo-06, under Mode Engineering (Pvt) Ltd on 27/9/2018.

3. Green Building Concept

We are going with the Green Building concept as a Corporate Member of the Green Building Council on 11/09/2019.

2. Green Building Concept

We received a certificate of industrial registration on 08/11/2017 onwards from the industrial development authority.

1. Green Building Concept

Mode Engineering Pvt Ltd admitted a corporate member of the chamber of Construction industry Sri Lanka on 10/09/2018.

× Hot Line