"University of Jaffna" project.

Progress made relating to the “University of Jaffna" project.
– Roof installation work is going to complete
– M/R Roof Slab Shuttering work…!
20/03/2021

"University of Jaffna" project.

Progress made relating to the “University of Jaffna" project.
– Roof installation work
– Gutter slab masonry work
– M/R Roof Slab Shuttering work…!
08/03/2021

"University of Jaffna" project.

roof beam shuttering work is going on…!
08/01/2021

"University of Jaffna" project.

1st-floor concrete has been completed on 06/11/2020.

Sri Suboothi National School Battaramulla." project

 present site progress. #renovation 13/10/2020

"University of Jaffna" project.

Shuttering work 1st floor & reinforcement work for staircase 09/10/2020

"Samanakkanda Purana Viharaya, Payagala"

The roof work at the stage of finishing. 05/09/2020

"Sri Suboothi National School Battaramulla." project

present site progress. #Roof_fixing#
10/08/2020

Samanakkanda Purana Viharaya, Payagala

The Current Progress Of The Project … 07/08/2020

University of Jaffna project

Conservation of Single Storied Building into Three Storied Building and Completion of Exam Hall at Centre for Open & Distance Learning, University Of Jaffna. Contract value 22.8 Million. The date of commencement on 15th June 2020.

Canal Reservation at Uttarananda Mawatha Project...

The progress of interlock paving with landscaping pedestrian facilities along the canal reservation at Uttarananda Mawatha….

Sri Suboothi National School, Battaramulla

The progress of works in the site…

Uttarananda Mawatha Project...

The progress of interlock paving with landscaping pedestrian facilities along the canal reservation at Uttarananda Mawatha….

Sri Suboothi National School, Battaramulla

The progress of Parapet wall construction works in the site…

Canal Reservation at Uttarananda Mawatha

The progress of paving interlock works in the site…

Samanakkanda Purana Viharaya, Payagala

The current progress of the Project …

Canal Reservation at Uttarananda Mawatha

Stage I completed successfully and Stage II was started. The site area was cleaned and up to 22m Concrete Curb Leveled for Laying Interlock.

Repair Works at Sri Suboothi National School Battaramulla

Modernization of Schools under the Nearest School
Repair Works at Sri Suboothi National School, Battaramulla under the NSBS program initiated by the Ministry of Education. Contract value 16 Million. The date of commencement on 10th July 2019.

Samanakkanda Purana Viharaya, Payagala

Conservation of Image House at Samanakkanda Purana Viharaya, Payagala awarded by the Central Cultural Fund (CCF) – Ministry of Housing Construction & Cultural Affairs. Contract value 22.2 Million. The date of commencement on 25th May 2019.

Renovation of Principal’s Office at Kalutara Vidyalaya.

Mode Engineering ( Private ) Limited has been awarded the contract for “ Renovation of Principal’s Office at Kalutara Vidyalaya “ initiated by the Ministry of Education under the “ Nearest School Best School “ Program. Contract value 4.2 Million. The date of commencement on 22nd April 2019.

Completed Projects- Mode Engineering

Canal Reservation at Uttarananda Mawatha

Pedestrian Facilities along the Canal Reservation at Uttarananda Mawatha under the Fort Development Project -Pedestrian Web Stage IV awarded by the Urban Development Authority (UDA) has been completed on 30th June 2020.th March 2020.

Canal Reservation at Uttarananda Mawatha

Pedestrian Facilities along the Canal Reservation at Uttarananda Mawatha under the Fort Development Project -Pedestrian Web Stage IV awarded by the Urban Development Authority (UDA). Contract value 9.4 Million. The date of commencement on 09th July 2019.

Kalutara Maha Vidyalaya, Kalutara

Renovation of Principal’s Office, Kalutara Maha Vidyalaya, Kalutara under the NSBS program initiated by the Ministry of Education. Contract value 3.59 Million. The works completed on 11th March 2020.

Vivekananda Maha Vidyalaya Colombo

Construction & Converting of Two Classroom Building in to Smart Classroom Building in Vivekananda Maha Vidyalaya Colombo under the NSBS program initiated by the Ministry of Education. Contract value 6.3 million. The works completed on 02nd May 2019.

University of Sri Jayewardenepura

Improving of Parking Facilities of Vehicles at University of Sri Jayawadanapurapura. Contract Value 7.2 Million. The works completed on 01st April 2019.

University of Ruhuna, Hapugala

Improving Drainage System at New Academic Quarters Area and Renovation works in three Academic Departments & Hostel a in the Faculty of Engineering, University of Ruhuna, Hapugala. Contract Value 4.5 Million. The works completed on 11th March 2019.

University of Sri Jayewardenepura

Aluminum Partitioning works of Administration Building in University of Sri Jayewardenepura. Contract Value 7.2 Million. The works completed on 10th March 2019

Water’s Edge, Battaramulla

Construction of Bar Counters at proposed Sports Bar & Restaurant at Waters Edge. Contract Value 3 Million. The works completed on 15th February 2019.

University of Ruhuna, Matara

University of Ruhuna, Wellamadama, Matara
Renovation Works in Dean Office, Santhagara Canteen, and Department of English & Sociology at the Faculty of Humanities & Social Sciences, University of Ruhuna. Contract Value 4.5 Million. The works completed on 02nd January 2019.

University of Ruhuna, Matara

In an existing Building to use as a Canteen
University of Ruhuna, Wellamadama, Matara
Improvement Works in an existing Building to use as a Canteen at the Faculty of Fisheries and Marine Sciences, University of Ruhuna. Contract Value 2.7 Million. The works completed on 21st December 2018.